Power on the ACTAS Px60
- Select the “Test” tile on the touch screen to create a new job.
ACTAS Px60 · Quick start
Create or select a switchgear template, configure dual-ground timing, run a timing test, and save the job.
Download PDF GuideSelect “New switchgear” to create a new template. To select an existing template and begin testing, jump to step 11.
In the upper-right corner of the screen, press the “+” icon to create a new template.
Specify the switchgear manufacturer and model.
Select the “Construction” tab to specify breaker details.
Select the “Tests” tab, then select the “Timing” tab from the list on the left.
Select the “Analysis” tab.
Select the “Main contacts” tab to designate the time-zero reference point as either the command signal or coil-current pickup. Close- and opening-speed measurement parameters can also be configured under this tab.
Select the “Connections” tab, then select “Edit default connections.”
Press the save icon at the top right of the screen.
Select the template from the list to begin testing.
Once the template has been selected, tests may now be performed.
Select the “Timing” tile.
Press the back arrow at the top left of the screen.